High Angle belt conveyor is a kind of equipment that can transport bulk materials at a large Angle or even vertically. it adopts wavy flange conveyor to achieve high Angle conveyor. has the characteristics of compact structure, small area of , easy maintenance and so on. this conveyor is widely used in coal, chemical, , , building materials, metallurgy, power, , light industry, food , , port ships, and other industries, can in 15 ℃ to + 40 ℃ environment humidity within the scope of delivery the mass density of 0.5 2.5 t/m3 of all kinds of material. For materials with special requirements, such as high temperature, containing acid, alkali, oil substances or organic solvents and other components of the material, need to use special conveyor belt.
The drive pulley drives the conveyor belt rotating, the movement of conveyor belt relies on the frictional force between the drive pulley and the conveyor belt to transport materials to the discharge end,thus continuous material flow is formed.
Product Photo
Preparation before the test run
(1) First check whether the installation is correct and whether all the fastening parts are loose.
I think this step is necessary, perhaps many users do not understand, but countless cases tell us that many accidents are caused by a certain part is not installed in place. Therefore, in order to ensure the safety of the operator, we must double check to ensure safety.
(2) Check whether the lubrication of the rotating friction parts is good, and it is strictly prohibited to run without lubrication.
The motor running without lubrication will cause the motor to heat up, and in serious cases it will even burn the motor, so be sure to check the lubrication of the rotating friction parts.
2. No-load experiment:
The new machine or the large Angle belt conveyor after overhaul should be carried out empty load test running test before being put into production and use, and the running time should not be less than 1 hour. In the experiment, the conveyor belt shall not slip, run off at both ends, run off in the middle or run off to one side after normal operation.
Three, high Angle belt conveyor full load experiment:
After the new machine or overhaul of the large Angle belt conveyor, after the no-load experiment operation meets the technical requirements, it should be carried out for 4 hours of full load operation experiment. There should be no malfunction during operation. Only then can it be delivered for acceptance.
The above is the high Angle belt machine test preparation work, the test is completed, if there is a problem, it needs to be re-debugging or maintenance, if there is no problem, it can be put into production